Hainan for a period of 20 days of sea-crossing cable end of comprehensive test
This newspaper haikou on May 11 (reporter Liang Zhenjun correspondent Lin Shiliang Chen Quanzhi) the reporter learns from the province's hall today, 20 days of sea-crossing cable integrated detection work has ended, the new equipment to replace complete networking, start, after the impact power and debugging job, sea-crossing cable at 2 PM on May 8 recovery and hainan interconnection.
Sea-crossing cable suspended during the comprehensive detection, the hainan power grid into the isolated net running, under the joint efforts of all parties concerned, by fully tap production potential and optimizing the grid scheduling effective measures, such as the hainan power grid through the test of the isolated net running safe and to achieve the safe and stable operation and reliable power supply.
On June 30, 2009, Asia construction scale first, submarine cable joint length same level as the world's longest sea-crossing interconnection project 500 kv hainan networking project completed and put into operation, across the qiongzhou strait in the south main electric power grid and the hainan power grid at the bottom of the sea "in hand", hainan from her for nearly a century of history "power island", the hainan power grid's ability to resist risk ability and the power supply security greatly ascend.